4D BIM: linking the model to the construction programme

4D BIM links the elements of a 3D building model to the activities of a construction programme, so the planned sequence can be played back as an animation. Planners use it to check the order of work, test site logistics and explain the plan to people who do not read Gantt charts.

Aerial view of a construction site with two red tower cranes, timber-frame blocks and stacked wall panels
Aerial view of a construction site with two red tower cranes, timber-frame blocks and stacked wall panels. Photo: Wikideas1, CC0

How 4D BIM links the model to the programme

A construction programme, called a schedule in many countries, lists activities with durations and dependencies, such as pouring the level 2 slab or installing the level 3 risers. 4D software imports it from a planning tool and links each activity to the elements it builds. Rules do most of the linking, for example by matching a location code on each element to a code in the activity, because links made one by one have to be redone whenever activities are split or renamed.

Temporary works need modelling too. Scaffolding, propping, excavation and cranes are usually absent from design models, so the planner adds them with their own install and remove activities.

Line-of-balance chart A line-of-balance chart with floors on the vertical axis and weeks on the horizontal axis: sloped lines for the frame, facade and partitions climb through the floors, and a circle marks where the faster partitions line would cross the slower facade line, putting both trades on the same floor in the same week. Floors 1 6 Weeks Frame Facade Partitions Same floor, same week
Fig. 4 Line-of-balance chart

Splitting the model by location

Design models and programmes divide the building differently. An external wall may be modelled as one object from ground to roof and a slab as one piece per floor, yet the contractor builds the wall storey by storey and pours the slab in bays between construction joints. Unless such elements are split first, the whole wall appears on the day its first storey starts.

A location breakdown structure (LBS) gives the split a logic: building, then floor, then zones within each floor, often following pour bays or fire compartments. Each element gets a location code, each activity is planned per location, and linking becomes a matter of matching codes.

Concrete pump placing one bay of a garage floor slab while the bays poured earlier have already cured
Concrete pump placing one bay of a garage floor slab while the bays poured earlier have already cured. Photo: Bill Alden, CC BY-SA 2.0

Line of balance and takt planning

Location-based planning draws the programme as lines. In a line-of-balance chart, locations usually run up the vertical axis and time along the horizontal. Each trade is a line climbing through the floors, and its slope shows its production rate. Where a fast trade's line would cross a slower one ahead of it, both would be working in the same place, so the planner delays or slows the faster trade.

Takt planning divides the building into areas with roughly equal amounts of work, and every trade spends the same fixed time, the takt, in each area before moving on, like the wagons of a train. A 4D view helps check that the areas really are equal, since a plant room or stair core inside one zone can make it far slower than the rest.

Site logistics in 4D

4D models are also used to plan the site itself. The tower crane is modelled with its jib radius, and the planner checks that each heavy lift, such as precast stairs or a rooftop chiller, falls within the radius at which the crane can carry that weight, because capacity drops as the load moves out along the jib. Laydown areas, hoists, delivery routes and pedestrian access all change as the building grows.

Prefabrication moves the pressure to deliveries. Bathroom pods and panels cut by machine must arrive in the order they will be lifted, and the 4D model shows whether a laydown area will still exist when they do. Time-based conflicts like these are the scheduling side of clash checking between models.

What 5D adds

5D links cost to the same model and programme. Quantities from the model, such as concrete volumes and door counts, are multiplied by rates, and because each element is tied to an activity, the cost can be spread over time as a forecast of spending. The estimate inherits every modelling error, so a slab modelled too thin goes straight into the figures. Labels beyond 5D, such as 6D and 7D, mean different things in different sources.

Worked exampleSequencing a five-storey concrete office

Hypothetical project. A five-storey office has a concrete frame, a central core and one tower crane. The contractor wants the facade to follow the frame floor by floor without trades meeting.

  1. 01

    The planner splits each slab into two pour bays and the core walls at every floor, then gives every element a location code such as L3-A.

  2. 02

    Activities are linked by matching codes, and the frame, the facade and the partitions appear as waves climbing the building.

  3. 03

    Playback shows facade panels due on level 2 while back-propping for the slabs above still fills that floor, leaving no room to land and fix them.

  4. 04

    The crane check shows that the heaviest corner panels lie beyond the crane's capacity at that radius, so a mobile crane is booked for them.

  5. 05

    In the revised line-of-balance chart the facade line no longer crosses the propping-removal line, and the animation is used to brief the subcontractors.

Where it falls short

  • An animation looks convincing whatever its quality. Loose links or an unsplit model produce a sequence nobody will follow on site.
  • 4D shows when work happens, not how many people or machines it needs, unless labour and plant are planned separately.
  • Curing times, weather, inspections and long lead times live in the programme logic and cannot be seen in the 3D view.
  • When the programme is revised and the links are not refreshed, the 4D model drifts away from the plan and people stop trusting it.

Key terms

Construction programme
The planned list of construction activities with their durations and dependencies, called a schedule in many countries.
Location breakdown structure (LBS)
A hierarchy of locations, such as building, floor and zone, used to split both the model and the programme so that they match.
Line of balance
A chart with locations on one axis and time on the other, in which each trade is a sloped line and crossing lines warn of trades meeting.
Takt time
The fixed time every trade spends in each work area before moving to the next one, so that trades follow each other at a steady rhythm.
Temporary works
Structures needed only during construction, such as scaffolding, propping and excavation support, often missing from design models.
5D BIM
Linking cost to the model and programme, so that quantities times rates give an estimate that can be spread over time.

All 86 terms in the glossary

Questions

What is the difference between 4D and 5D BIM?

4D links model elements to the construction programme, so the model shows what is built when. 5D adds cost by multiplying model quantities by rates and spreading the result over the same programme. Both depend on a model split the way the work is actually built.

Does 4D BIM need a detailed model?

It needs a model split the way the work is built more than it needs fine detail. Slabs divided into pour bays and walls divided by storey matter more than detailed windows. Temporary works and cranes often have to be modelled from scratch.

Who builds the 4D model?

Usually the main contractor's planner or digital construction team, working from the design models and the contractor's own programme. Designers rarely produce it, because the sequence depends on how the contractor intends to build.