Clash detection in BIM: how coordination finds problems before site

Clash detection is the automated search for places where elements from different discipline models collide or come too close, such as a duct passing through a beam. The discipline models are combined into one federated model, software tests chosen sets of elements against each other, and the team reviews the results before anything is built.

Steel cable trays, cable ladders and bundled cables crossing each other under a concrete ceiling
Steel cable trays, cable ladders and bundled cables crossing each other under a concrete ceiling. Photo: Leotard, CC0

Hard, clearance and workflow clashes

A hard clash is a physical overlap, such as a pipe through a column or a cable tray through a duct. A clearance clash, also called a soft clash, is an element inside a space that must stay free: the access zone in front of an electrical panel, the room needed to withdraw a fan coil unit, or a buffer for insulation that was never modelled.

A workflow clash concerns time, such as two trades booked into the same ceiling void in the same week. These are found by linking the model to the construction programme, the subject of construction sequencing in 4D.

Hard clash and clearance zone Section through a ceiling void: a duct crosses the lower part of a steel beam under the floor slab, the overlap is shaded as a hard clash, and a dashed clearance zone surrounds a valve on a pipe above the ceiling. Floor slab Steel beam Duct Hard clash Clearance zone Valve Pipe Ceiling
Fig. 3 Hard clash and clearance zone

How clash detection works

Each discipline exports its model at an agreed time and the coordinator combines them into a federated model, while each part stays owned by its author. All models must share the same origin and orientation, or the results mean nothing. Some teams federate native files, others use exports in the open IFC format.

The coordinator then writes tests between selection sets, such as structure against ductwork. Rules exclude pairs that are meant to touch, like a pipe and its own fittings or a beam and the column it bears on. A tolerance, agreed by the team in millimetres, makes the software ignore overlaps shallower than that, so elements modelled flush do not report as collisions.

Why thousands of clashes are often a handful of problems

A first run on a new federated model can report thousands of clashes from a few causes. A drainage run modelled at the wrong level clashes with every joist it crosses, one result per joist. Columns modelled by both the architect and the structural engineer report as clashes along every grid line until a responsibility matrix says they belong to the structural model alone.

Coordinators group results by level, zone or system, or by the element that appears most often, and raise one issue per real problem. The number worth tracking from week to week is open issues, since the raw clash count rises and falls with how the tests are set up.

What clash tests miss

Tests only see what has been modelled. Duct and pipe insulation is often left out, so a duct that clears a beam on screen hits it once the lagging goes on. Hangers, brackets and the space a fitter needs to reach a flange are rarely modelled at design stage. Teams either model insulation as real thickness or run a clearance test with a buffer equal to it.

Penetrations need their own check. If a riser passes through a slab with no opening modelled, the hole may later be cut through reinforcement. Many teams therefore require every service opening, known in the UK as a builder's work opening, to be modelled and approved by the structural engineer.

Mechanical room ceiling packed with foil-insulated ducts, lagged pipes, cable trays and hangers
Mechanical room ceiling packed with foil-insulated ducts, lagged pipes, cable trays and hangers. Photo: Wolfmann, CC BY-SA 4.0

Coordination meetings and issue tracking

In a typical cycle, models are uploaded at a fixed point, tests run, results are grouped, and a coordination meeting gives each issue an owner and a due date. Issues return to the authors as BCF topics that can be opened at the right view in their own software. Prefabricated risers and service modules made off site raise the stakes, because a clash found after manufacture means rebuilding a module.

Worked exampleA duct through a beam in a four-storey school

Hypothetical project. A four-storey school has a steel frame and a main supply duct along each corridor ceiling. The first coordination run reports several hundred hard clashes between ductwork and structure.

  1. 01

    Grouping by level and element shows that almost all of them involve the corridor duct crossing the same line of secondary beams, repeated on each floor.

  2. 02

    The duct was modelled to a ceiling height from an earlier design, before the structural engineer deepened the corridor beams to span further.

  3. 03

    Two fixes are possible: lower the duct and lose ceiling height, or pass it through openings in the beam webs. One BCF issue goes to both engineers.

  4. 04

    At the coordination meeting the architect accepts a slightly lower corridor ceiling. The duct is lowered and its insulation modelled as real thickness.

  5. 05

    The next run clears the corridors, and a clearance test around the access panels of the fire dampers shows two remaining conflicts, which become new issues.

Where it falls short

  • Software finds overlapping geometry, not design problems. A route that clears every beam yet leaves no room to maintain a valve passes a hard clash test.
  • Results depend on what was modelled. Missing insulation, supports and fixings give false confidence.
  • Clash counts are easy to report and easy to misread; a falling count may only mean the tests were narrowed.
  • Each cycle takes time from every discipline, and a clash found after shop drawings or manufacture costs far more to fix than one found in design.

Key terms

Federated model
A combined model assembled from separate discipline models for review, in which each part stays owned and edited by its author.
Hard clash
Two elements occupying the same space, such as a pipe passing through a beam.
Clearance clash
An element inside a zone that must stay free for access, maintenance or insulation, even though nothing physically overlaps. Also called a soft clash.
Clash tolerance
The overlap depth below which software ignores an intersection, agreed by the team in millimetres so that elements meant to touch are not reported.
Selection set
A saved group of elements, such as all sprinkler pipes on one level, used as one side of a clash test.
Builder's work
UK term for openings, sleeves and other work by the main contractor that lets services pass through walls and slabs.

All 86 terms in the glossary

Questions

Who is responsible for clash detection?

A BIM coordinator runs the tests and chairs the review, usually on the lead designer's side during design and on the main contractor's side during construction. Each designer stays responsible for fixing clashes in their own model. The BIM execution plan should record these roles.

What tolerance should a clash test use?

There is no universal value. Teams agree a tolerance in millimetres for each test, small enough to catch real overlaps and large enough to ignore elements modelled flush, and record it so every run uses the same settings.

Does clash detection replace installation drawings?

No. It checks the models against each other, so its value depends on how closely they match what will be installed. Installation drawings from the trades and checks on site are still needed, especially for supports and final routes.